Zachary Community Park is open to the public and under construction of two wonderful projects. The community playground is underway with anticipated completion by the end of 2015. This community playground will include a large play area with swings, climbers, spinners and more. There will be adult fitness equipment near the walking path at the lake. Two pavilions will provide shaded seating for the play area along with multiple benches and lawn areas.


Also, the construction of a splash pad will begin in October 2015. The splash pad will have plenty of shaded seating under two pavilions situated around the water play area. We invite you to join us in the spring of 2016 when the splash pad will be complete and open for play.

Progress Report

July 2015

  • Splash Pad documents – DHH permit received – Out to Bid, bid opens August 14
  • Playground Area just starting – Ground-breaking held June 19

August 2015

  • Splash Pad Bid opened August 14 within budget
  • Playground Area – 30% complete

September 2015

  • Splash Pad Bid Notice to Proceed Oct 1
  • Playground Area – 25% complete

October 2015

  • Splash Pad Bid Notice to Proceed Oct 19
  • Playground Area – 30% complete

November 2015

  • Playground Area – 50% complete
  • Splash Pad Bid – Construction starting

December 2015

  • Playground Area – 60% complete
  • Splash Pad Bid – 40% complete

January 2016

  • Playground Area – 80% complete
  • Splash Pad Bid – 75% complete

February 2016

  • Playground Area – 90% complete
  • Splash Pad Bid – 90% complete

April 2016

  • Grand Opening for playground/splash pad held April 22
Related Links

Click here to view the Final Master Plan

Capital Improvements Progress Report