Project Updates

  • May 2019 - Public input survey being developed
  • June 2019 - Public input survey conducted
  • July 2019 - In Design - Construction to start soon
  • November 2019 - Project on HOLD
  • June 2020 - 50% Complete;
  • July 2020 - 75% Complete; Concrete being poured, awaiting playground equipment installation
  • September 2020 - 80% Complete; awaiting playground installation and punch list items to be completed
  • January 2021 - Playground work to begin in February
  • February 2021 - 80% Complete; awaiting drier weather for playground installation
  • March 2021 - 90% Complete; playground equipment installed and EWF to be laid down
  • April 2021 - 95% Complete; playground equipment installed and EWF to be laid down and drainage to be installed
  • June 2021 - 99% Complete; regrassing pending drier weather conditions
  • October 2021 - 100% Complete; park open to public.

Completed Fall 2021