Madison Ave Park Improvements
![](/assets/PlanningandEngineering/MadisonAve/MadisonAveRendering2024_1.jpg)
![](/assets/PlanningandEngineering/MadisonAve/MadisonAveRendering2024_2.jpg)
New Features in Current Project Improvements:
- CONNECTING walks
- Basketball IMPROVEMENTS
- NEW Playground Equipment
Project Updates
- July 2023 - Public Survey for park improvements issued to the public. View Survey Results
- October 2023 - preparing construction documents
- November 2023 - RFQ out for bid
- January 2024 - new playground equipment has been selected; installation expected mid-2024
- April 2024 - CCD doing demolition and site prep work
- May 2024 - concrete for new walks
Estimated Completion for Current Improvements: February 2025