Boulevard de Province Park - Improvements
New Features in Current Project Improvements:
- New Playground
- New ADA Site Improvements
- New Site furnishings
- New Water Fountain
Project Updates
- August 2019 - Public Input Survey conducted
- September 2019 - In design
- February 2021 - design phase completed, new playground equipment being purchased.
- April 2021 - 30% Complete; site work underway, playground closed to the public.
- June 2021 - 70% Complete; site furnishings completed: refurnished pavilion, new picnic tables and benches, new drinking fountain has been installed, awaiting playground equipment to be installed
- July 2021 - 70% Complete; new playground equipment to be installed in late Summer 2021.
- August 2021 - 90% Complete; new playground equipment installed and CCD working on safety surfacing.
- November 2021 - 100% Complete; reopened for public use