Forest Community Park -- Park Improvements

Visit Facility Page

Forest Community Park Map showing location of boardwalk
(Click to enlarge)

New Features in Current Project Improvements:

  • New 900' accessible boardwalk on hiking trail

Project Updates:

  • February 2022 - Construction underway
  • May 2022 - Construction Complete

Completed May 2022


 

Previous Improvements

Features

  • new play area
  • new lobby/reception area
  • new meeting rooms
  • new multi-purpose room
  • new restrooms
  • new storage space
  • new heat & air conditioning
  • resurfaced gym floor

COMPLETED SPRING 2020(Click to view project timeline)

Project Updates

  • APRIL 2016 - Bid issued
  • JUNE 2016 - Notice to Proceed issued to Wharton-Smith, Inc.
  • JULY 2016 - Groundbreaking ceremony held
  • AUGUST 2017 - Construction experiencing delays due to weather.
  • SETPEMBER 2017 - Construction estimate at 85% compleition
  • OCTOBER 2017 - Contractor wrapping up scope; permitting, etc. next.
  • JANUARY 2018 - Flood repairs underway for new construction
  • NOVEMBER 2018 - Bid for flood repairs to existing structure awareded to ANR Construction
  • JANUARY 2019 - Mold abatement underway. Flood repair immediately to follow.
  • FEBRUARY 2019 - Remediation complete; Repair to existing structure underway
  • MARCH 2019 - 20% Complete, Remediation complete; repair to existing structure underway
  • APRIL 2019 - 40% Complete, Brick exterior underway
  • JUNE 2019 - 65% Complete, Working in gym / HVAC System
  • JULY 2019 - 80% Complete
  • SEPTEMBER 2019 - 95% Complete
  • OCTOBER 2019 - 99% Complete
  • DECEMBER 2019 - 99% Complete, Finalizing construction
  • FEBRUARY 2020 - Construction Complete