New Features in Current Project Improvements:

  • NEW Playground Equipment
  • NEW Site Improvements
  • NEW Picnic Tables
  • NEW Connecting Walks and ADA Accessible Walks
  • NEW Drinking Water Fountain
  • Renovated Restroom building
  • Improved parking lot

Project Updates

  • June 2021 - Project in design, public online survey closes 06/20/21 and will take data to finalize design.
  • July 2021 - Project in design using input from public survey and ADA report.
  • December 2021 - Construction Underway
  • February 2022 - 25% Complete; Concrete poured for connecting walks along baseball field, grading for playground area is completed, layout for playground equipment has begun
  • May 2022 - 75% Complete; Concrete poured for connecting walks along baseball field has been completed. Playground equipment to be installed by Summer 2022.
  • June 2022 - 75% Complete; Awaiting playground equipment to be installed in Summer 2022.
  • August 2022 - 95% Complete; Playground equipment installed, contractor completing punch list items.
  • October 2022 - 100% Complete; Playground Equipment has been installed and all site improvements finished. Playground is open to the public

Completed October 2022