Lafitte Street Park - Improvements
New Features in Current Project Improvements:
- New playground equipment and wood mulch safety surfacing
- New parking configuration
- New concrete walking loop
- New Picnic tables and benches and associated sidewalks
- New Drinking fountain and associated plumbing
- Improved Site grading and drainage
Project Updates
- October 2019 - Public Input Survey Conducted
- November 2019 - In design
- December 2021 - Construction Underway
- February 2022 - 5% Complete; 1st phase of walking loop concrete poured and complete, construction underway for playground equipment
- May 2022 - 70% Complete; Playground equipment has been installed and completed.
- June 2022 - 80% Complete; Concrete pours to be completed by In-House CCD. Concrete pour include walking loops / paths and picnic pads. Landscape hydroseeding and tree planting will be completed soon.
- August 2022 - 90% Complete; Playground equipment has been installed, landscape hydroseeding and tree planting to be completed in the fall.
- NOVEMBER 2022 - 100% Complete; project is completed!
COMPLETED NOVEMBER 2022