Lafitte Street Park - Improvements

Visit Facility Page

New Features in Current Project Improvements:

  • New playground equipment and wood mulch safety surfacing
  • New parking configuration
  • New concrete walking loop
  • New Picnic tables and benches and associated sidewalks
  • New Drinking fountain and associated plumbing
  • Improved Site grading and drainage

Project Updates

  • October 2019 - Public Input Survey Conducted
  • November 2019 - In design
  • December 2021 - Construction Underway
  • February 2022 - 5% Complete; 1st phase of walking loop concrete poured and complete, construction underway for playground equipment
  • May 2022 - 70% Complete; Playground equipment has been installed and completed.
  • June 2022 - 80% Complete; Concrete pours to be completed by In-House CCD. Concrete pour include walking loops / paths and picnic pads. Landscape hydroseeding and tree planting will be completed soon.
  • August 2022 - 90% Complete; Playground equipment has been installed, landscape hydroseeding and tree planting to be completed in the fall.
  • NOVEMBER 2022 - 100% Complete; project is completed!

COMPLETED NOVEMBER 2022