Project Updates

  • November 2020 - Project in contracting
  • January 2021 - Notice to Proceed issued early January, construction underway
  • February 2021 - 25% Complete; pool plaster demolition is complete and forming up building slab and concrete line queues
  • March 2021 - 65% Complete; about to install plaster and building slab is complete. Working on building concrete blocks for the building
  • April 2021 - 75% Complete; Building block work and roof extention complete. Interior improvements underway.
  • June 2021 - 98% Complete; Project is substanially complete, punch list and close out needs to be completed
  • August 2021 - 100% Complete; Punch list items to be completed after season.

COMPLETED AUGUST 2021


 

Previous Improvements

LIBERTY LAGOON PHASE 2 RENDERING

Liberty Lagoon was a part of the original Imagine Your Parks Master Plan. Phase II of the Liberty Lagoon improvements (part of Imagine Your Parks 2) included a significant park expansion with new features and amenities. The expansion would also increase the maximum capacity of the park from 600 to 900 guests.

Features

  • NEW picnic tables with umbrells
  • NEW admission entrance gate
  • NEW restrooms and changing rooms
  • NEW FlowRider surfing machine
  • NEW thrill-based slides (2)
  • ADDITIONAL deck space
  • ADDITIONAL shade coolbrellas

COMPLETED MARCH 2017(Click to view project timeline)

Project Updates:

  • JANUARY 2016 - Bid issued
  • MARCH 2016 - Notice to proceed issued to Wharton-Smith, Inc.
  • APRIL 2016 - Groundbreaking ceremony held
  • MARCH 2017 - Construction complete, facility testing underway
  • APRIL 2017 - Ribbon cutting ceremony held April 22