Maplewood Park - Improvements

Visit Facility Page


(Click to enlarge)

Project Features:

  • NEWPlayground Equipment
  • NEW Fitness Equipment
  • INCREASED Shade
  • NEW Connecting Walks"

Project Updates

  • January 2020 - In design, Public Meeting end of January
  • March 2020 - Conducted online public input survey. Download Results Here
  • APRIL/MAY 2020 – Analysis of Online Survey, Schematic Design, Design Development
  • September 2020 - Construction set to begin 2021
  • February 2021 - Project going out to bid
  • March 2021 - Project Bid Opening, 03/25, awaiting bid tab and recommendation
  • April 2021 - Bid contractor awards going before Commission for approval in April
  • June 2021 - 5% Complete, project underway: demolilion and layout have begun.
  • July 2021 - 5% Complete, continuing construction
  • August 2021 - 10% Complete, area has been prepared for playground equipment and awaiting shipment of play equipment.
  • November 2021 - 20% Complete, Contractor has completed drainage work and prepared playground area, awaiting shade structure and new playground equipment to arrive on site.
  • February 2022 - 90% Complete, Shade structure completed, playground equipment completed, working on site furnishing and grading and completing the playground surfacing.
  • May 2022 - 95% Complete, Contractor is addressing punch list items.
  • June 2022 - 95% Complete, Contractor is addressing punch list items.
  • August 2022 - 99% Complete, Continuing finishing items to get ready for Ribbon Cutting.
  • NOVEMBER 2022 - 100% Complete, project complete! Ribbon Cutting to be planned 

COMPLETED NOVEMBER 2022


 

Previous Improvements

Features

  • FLOOD RENOVATIONS
  • RENOVATED pavilion with restrooms

COMPLETED APRIL 2021 (Click to view project timeline)

Project Updates:

  • NOVEMBER 2019 - Abatement underway
  • JANUARY 2020 - Abatement Complete; Recreation Center to bid soon
  • APRIL 2020 - Construction underway
  • JUNE 2020 - 10% Complete
  • SEPTEMBER 2020 - 50% Complete; construction on new entryway and installation of new basketball goals
  • NOVEMBER 2020 - 55% Complete; construction continuing
  • JANUARY 2021 - 80% Complete; gym renovations and multi-purpose room addition complete, roof under construction
  • FEBRUARY 2021 - 90% Complete; gym renovations and multi-purpose room addition complete, roof complete, installation steel framing for signage fabrication underway
  • APRIL 2021 - 100% Complete; Maplewood recreation building is completed! P&E will give to Recreation to open to the public when they ready. Playground construction to begin in late May.