Rue Leboeuf Park - Park Improvements

Visit Facility Page


(Click to enlarge)
 

New Features in Current Project Improvements:

  • NEW playground equipment
  • NEW engineered wood fiber safety surface
  • NEW connector walks
  • NEW drinking fountain
  • NEW site furnishings
  • RENOVATED existing picnic shelter
  • RENOVATED ADA parking

Project Updates

  • May 2019 - Public Input survey developed and conducted.
  • June 2019 - Planning underway
  • August 2019 - Construction underway
  • November 2019 - 30% Complete, Playground equipment to be installed soon
  • January 2020 - 90% Complete, Playground equipment installed, new connector walks, new drinking fountain to be installed soon
  • March 2020 - 95% Complete, Playground equipment installed, new connector walks, new drinking fountain to be installed soon
  • April 2020 - Construction Complete

COMPLETED APRIL 2020