Spain Street Park - Improvements

Visit Facility Page


(Click to enlarge)

New Features in Current Project Improvements:

  • New playground
  • New picnic shelter
  • Refurbished Basketball Court
  • New connector walks
  • New picnic tables and citrus trees
  • New game table and surface mount

Project Updates

  • June 2017 - Public meeting held
  • July 2017 - Master plan presented at public meeting
  • September 2017 - Construction started
  • February 2018 - Concrete pour in progress; Shelter frame installed
  • March 2018 - Playground instalation
  • July 2018 - Grand Opening with Mid City Studios

COMPLETED JUNE 2018