Acadian Thruway - Park Improvements

Visit Facility Page


(Click to enlarge)

 

New Features in Current Project Improvements:

  • New Playground
  • Improved Basketball Court
  • Improved Walking Path
  • New Security Lighting
  • New Fence & hedges

Project Updates

  • May 2018 - Park identified for improvements;
  • August 2018 - Online public input survey conducted
  • September 2018 - Project in design
  • November 2018 - Construction Underway
  • December 2018 - Construction 20% Complete
  • January 2019 - 25% Complete, waiting to pour concrete for walking path. Pending dry weather.
  • February 2019 - 90% Complete, fencing left
  • March 2019 - 95% complete, Ornamental Fencing being put in, Sod & Seed next
  • April 2019 - 99% complete, Final paint, clean up, Finishing touches on fence, New signage completed

Completion Date: Spring 2019