New Features in Current Project Improvements:
- New Playground Equipment
- New ADA Connector Walks
Project Updates
- September 2020 - Project in design
- November 2020 - Public input survey conducted
- February 2021 - restroom renovations are underway, new playground equipment upcoming
- March 2021 - Restrooms Renovations completed! New playground equipment upcoming, playground closed to the public
- April 2021 - New playground equipment out for bidding, playground closed to the public
- June 2021 - New playground equipment to be installed.
- July 2021 - Existing park restroom was renovated to make accessibility for all and new playground equipment to be installed in Fall 2021.
- November 2021 - New playground equipment to be installed, connecting paths in progress
- February 2022 - New playground equipment to be installed in Spring 2022, due to manufacuring delays for playground equipment. CCD completed connecting paths.
- May 2022 - 100% Complete; Playground equipment installed.
Estimated Completion for Current Improvements: Spring 2022