Boulevard de Province Park - Improvements

Visit Facility Page


(Click to enlarge)

 

New Features in Current Project Improvements:

  • New Playground
  • New ADA Site Improvements
  • New Site furnishings
  • New Water Fountain

Project Updates

  • August 2019 - Public Input Survey conducted
  • September 2019 - In design
  • February 2021 - design phase completed, new playground equipment being purchased.
  • April 2021 - 30% Complete; site work underway, playground closed to the public.
  • June 2021 - 70% Complete; site furnishings completed: refurnished pavilion, new picnic tables and benches, new drinking fountain has been installed, awaiting playground equipment to be installed
  • July 2021 - 70% Complete; new playground equipment to be installed in late Summer 2021.
  • August 2021 - 90% Complete; new playground equipment installed and CCD working on safety surfacing.
  • November 2021 - 100% Complete; reopened for public use