Brookfield Avenue Park - Improvements

Visit Facility Page


(Click to enlarge)

 

New Features in Current Project Improvements:

  • New Playground Equipment
  • New Walking Loop

Project Updates

  • May 2019 - Public input survey being developed
  • June 2019 - Public input survey conducted
  • July 2019 - In design
  • November 2019 - Construction Underway
  • January 2020 - Construction 20% complete
  • March 2020 - 95% Complete, Playground equipment and walking loop installed. Crews finalizing improvements.
  • June 2020 - 98% Complete
  • September 2020 - 99% Complete, need to install benches and grass seed
  • February 2021 - 100% complete