Brookfield Avenue Park - Improvements
New Features in Current Project Improvements:
- New Playground Equipment
- New Walking Loop
Project Updates
- May 2019 - Public input survey being developed
- June 2019 - Public input survey conducted
- July 2019 - In design
- November 2019 - Construction Underway
- January 2020 - Construction 20% complete
- March 2020 - 95% Complete, Playground equipment and walking loop installed. Crews finalizing improvements.
- June 2020 - 98% Complete
- September 2020 - 99% Complete, need to install benches and grass seed
- February 2021 - 100% complete