Cadillac Street Park - Improvements
New Features in Current Project Improvements:
- NEW Playground Equipment
- NEW Fitness Equipment
- INCREASED Shade
- NEW Connecting Walks
Project Updates
- January 2020 - In design, Public Meeting end of January
- March 2020 - Conducted online public input survey. Download Results Here
- APRIL/MAY 2020 – Analysis of Online Survey, Schematic Design, Design Development
- September 2020 - construction to begin 2021
- February 2021 - Project going out to bid
- March 2021 - Project Bid Opening, 03/25, awaiting bid tab and recommendation
- April 2021 - Bid contractor awards going before Commission for approval in April
- June 2021 - 15% Complete, construction underway: pouring concrete connecting walks
- July 2021 - 20% Complete, construction continuing
- August 2021 - 30% Complete, installation of fitness equipment to be installed.
- November 2021 - 40% Complete, awaiting shade structure and new playground equipment to arrive on site.
- February 2022 - 98% Complete, shade structure completed, playground equipment completed, working on last punch list items.
- May 2022 - 98% Complete, Continuing contractor's and CCD punch list items.
- June 2022 - 98% Complete, Continuing CCD punch list items to finish project.
- August 2022 - 99% Complete, Continuing finishing items to get ready for Ribbon Cutting.
- February 2023 - 100% Complete; ribbon cutting to be scheduled