Cadillac Street Park - Improvements

Visit Facility Page


(Click to enlarge)

 

New Features in Current Project Improvements:

  • NEW Playground Equipment
  • NEW Fitness Equipment
  • INCREASED Shade
  • NEW Connecting Walks

Project Updates

  • January 2020 - In design, Public Meeting end of January
  • March 2020 - Conducted online public input survey. Download Results Here
  • APRIL/MAY 2020 – Analysis of Online Survey, Schematic Design, Design Development
  • September 2020 - construction to begin 2021
  • February 2021 - Project going out to bid
  • March 2021 - Project Bid Opening, 03/25, awaiting bid tab and recommendation
  • April 2021 - Bid contractor awards going before Commission for approval in April
  • June 2021 - 15% Complete, construction underway: pouring concrete connecting walks
  • July 2021 - 20% Complete, construction continuing
  • August 2021 - 30% Complete, installation of fitness equipment to be installed.
  • November 2021 - 40% Complete, awaiting shade structure and new playground equipment to arrive on site.
  • February 2022 - 98% Complete, shade structure completed, playground equipment completed, working on last punch list items.
  • May 2022 - 98% Complete, Continuing contractor's and CCD punch list items.
  • June 2022 - 98% Complete, Continuing CCD punch list items to finish project.
  • August 2022 - 99% Complete, Continuing finishing items to get ready for Ribbon Cutting.
  • February 2023 - 100% Complete; ribbon cutting to be scheduled