Cedarcrest Park - Improvements
New Features in Current Project Improvements:
- New Playground
- New ADA Site Improvements
- New Water Fountain
Project Updates
- August 2019 - Public Input Survey conducted
- September 2019 - In Design
- July 2020 - In Design
- November 2021 - Topo survey completed recently
- July 2023 - Community Public Meeting scheduled for July 25 and public survey is online. View Survey Results
- October 2023 - RFQ received for playground equipment. Project in contracting phase.
- December 2023 - Underway on construction. Playground equipment to be installed spring 2024.
- February 2024 - playground installed; finishing construction on playground portion.
- April 2024 - playground portion complete and reopened
Estimated Completion for Current Improvements: Summer 2024