Church Street Park - Park Improvements
New Features in Current Project Improvements:
- Repaired RECREATION CENTER (flood damage)
- NEW Gym Floor
Project Updates
- June 2021 - Project underway for recreation center flood repair, Notice to Proceed for contractor started 06/14/21, recreation center closed to the public
- July 2021 - 50% Complete; Abatement complete and new gym floors to be installed.
- August 2021 - 95% Complete; Punch list items to be completed.
- November 2021 - 100% complete
Previous Improvements
Features
- NEW sidewalk connectors
- ADDITIONAL recreation center rooms
- IMPROVED entry
COMPLETED JANUARY 2020 (Click to view project timeline)
Project Updates:
- JULY 2018 - Project out for bid; Bid awarded to BDS Construction
- AUGUST 2018 - Permitting
- OCTOBER 2018 - Notice to proceed issued to BDS Construction
- NOVEMBER 2018 - Construction underway
- DECEMBER 2018 - Demolition Phase
- JANUARY 2019 - Drainage, building slab addition, and utilities. Pending dry weather.
- MARCH 2019 - 15% complete, Foundation dug, Concrete pour, plumbing and treatments next, Electrical Utilities
- APRIL 2019 - 40% complete, Framing and concrete going up
- JUNE 2019 - 60% complete, Wall panels up
- JULY 2019 - 75% complete, Wall panels up, Windows / Doors, Construction Continues
- SEPTEMBER 2019 - 85% complete, Gym Floors Completed
- NOVEMBER 2019 - 95% complete, Site work to be completed
- JANUARY 2020 - Construction wrapping up