Cohn Arboretum - Improvements
New Features in Current Project Improvements:
- Renovated bungalow
Project Updates
- September 2020 - Project completed design phase, project to go out to bid soon
- November 2020 - Project in bidding
- February 2021 - 15% Complete, project underway and roof completed
- March 2021 - 20% Complete, construction continuing
- April 2021 - 40% Complete, abatement completed, construction continuing
- June 2021 - 80% Complete, renovation construction continuing
- July 2021 - 90% Complete, renovation construction continuing.
- August 2021 - 95% Complete, renovation construction continuing.
- November 2021 - 98% Complete, project is substantally completed, contractor is working on punch list items.
- February 2022 - 99% Complete, final inspections in February.
- May 2022- 100% Complete, building is completed. Recreation to take hold of building from P&E.
Completed Spring 2022
Previous Improvements
Features:
- Renovated historical building (including abatement)
COMPLETED SUMMER 2020 (Click to view project timeline)
Project Updates
- DECEMBER 2018 - Project in design
- JANUARY 2020 - Abatement advertised
- SEPTEMBER 2020 - 100% complete, lead containing paint stabilization complete