Project Updates
- March 2018 - Park identified for improvements; master plan design underway
- April 2018 - Constuction underway
- June 2018 - Walking path 75% done; pavilion under construction
- July 2018 - fitness equipment ordered
- August 2018 - Fitness Equipment being installed
- October 2018 - Preparation for sod
- December 2018 - Final sod added; project complete
Completed December 2018