Greenwell Springs Park - Improvements
New Features in Current Project Improvements:
- NEW Playground Equipment
- NEW Site Improvements
- NEW Picnic Tables
- NEW Connecting Walks and ADA Accessible Walks
- NEW Drinking Water Fountain
- Renovated Restroom building
- Improved parking lot
Project Updates
- June 2021 - Project in design, public online survey closes 06/20/21 and will take data to finalize design.
- July 2021 - Project in design using input from public survey and ADA report.
- December 2021 - Construction Underway
- February 2022 - 25% Complete; Concrete poured for connecting walks along baseball field, grading for playground area is completed, layout for playground equipment has begun
- May 2022 - 75% Complete; Concrete poured for connecting walks along baseball field has been completed. Playground equipment to be installed by Summer 2022.
- June 2022 - 75% Complete; Awaiting playground equipment to be installed in Summer 2022.
- August 2022 - 95% Complete; Playground equipment installed, contractor completing punch list items.
- October 2022 - 100% Complete; Playground Equipment has been installed and all site improvements finished. Playground is open to the public
Completed October 2022