Longfellow Park - Improvements
New Features in Current Project Improvements:
- New playground
- New bleachers
- Improved Basketball Court
- New walks & benches
- New picnic tables
Project Updates
- May 2017 - Park identified for improvements; planning phase initiated.
- August 2017 - Design consultant starting on schematic design. Public input in September
- February 2018 - Bid opened
- March 2018 - Notice to Proceed issued to The Luster Group LLC
- March 2018 - Demo & walk layout underway
- June 2018 - Construction substantially complete
- August 2018 - Grand Opening prep
- October 2018 - Grand Opening held
COMPLETED AUGUST 2018