Lovett Road Park Improvements
New Features in Current Project Improvements:
- NEW Dog Park
- NEW Rinse Dog Stations
- NEW Pavilions
- MORE Trees / Shade
- NEW Drinking Fountain
- NEW Fencing with SEPARATE small & large dogs areas
Project Updates
- January 2020 - In design, Topo survey completed
- March 2020 - Conducted online public input survey. Download Results Here
- APRIL/MAY 2020 – Analysis of Online Survey, Schematic Design, Design Development
- September 2020 - Project in design
- October 2020 - Project out to bid
- November 2020 - Project in contracting
- January 2021 - 2% Complete, construction project has begun
- February 2021 - 8% Complete, drainage construction has begun
- March 2021 - 30% Complete, pavilions have been installed and fence is partially installed
- April 2021 - 40% Complete, additional fencing and pavilion roof panels have been installed and sidewalks have been concreted poured.
- June 2021 - 50% Complete, additional fencing continuing and crushed stone has been installed in large dog section.
- July 2021 - 80% Complete, construction continuing. Fencing, crushed stone, and concrete has been completed.
- August 2021 - 90% Complete, project drainage and punch list items to be completed.
- November 2021 - 100% Complete, dog park project is completed. Set to reopen to the public December 2021
Previous Improvements
Features
- REPAIRED Flood damage
- NEW multi-purpose rooms with kitchenette & storage space
- NEW restrooms
- NEW heat & air conditioning in all rooms & gym
- NEW basketball goal systems
- NEW entry pavilion
- NEW roof
COMPLETED SPRING 2020 (Click to view project timeline)
Project Updates:
- JULY 2018 - Project out for bid; Bid awarded to BDS Construction
- AUGUST 2018 - Permitting
- OCTOBER 2018 - Construction underway
- DECEMBER 2018 - Demolition Phase
- JANUARY 2019 - Building slab addition and utilities. Pending dry weather.
- FEBRUARY 2019 - HVAC going in; walls going up on most of building; more slab work to happen due to poor soil quality
- APRIL 2019 - 40% Complete, Framing and concrete going up
- JUNE 2019 - 50% Complete, Framing and concrete going in, continuing construction
- JULY 2019 - 60% Complete, Roof installation & wall framing going up, continuing construction
- SEPTEMBER 2019 - 70% Complete, Continuing construction
- NOVEMBER 2019 - 80% Complete, Continuing construction
- JANUARY 2020 - 85% Complete, Continuing construction
- MARCH 2020 - March 2020 - 90% Complete, Continuing construction
- JUNE 2020 - 100% complete; Ribbon Cutting event postponed due to COVID-19
Features
- NEW Playground Equipment
COMPLETED FEBRUARY 2021 (Click to view project timeline)
Project Updates:
- SEPTEMBER 2020 - In contracting
- JANUARY 2021 - playground equipment to be installed in early 2021
- FEBRUARY 2021 - 100% Complete, playground has been installed