Bayou Manchac - Park Improvements

Visit Facility Page


(Click to enlarge)
 

New Features in Current Project Improvements:

  • NEW canoe/ kayak launch
  • New gravel drive
  • New fishing pier

Project Updates

  • November 2019 - Site survey completed, invasive trees to be removed
  • January 2020 - In Design Phase, Invasive trees removed
  • March 2020 - pending permitting
  • July 2020 - Project in design
  • September 2020 - Project awaiting permitting approval
  • October 2020 - Permitting approved, completing final design
  • February 2021 - working on cost estimates and bid documents
  • March 2021 - project in last stages of design, construction expected to begin in Summer 2021
  • April 2021 - awaiting opinion on access road to the kayak launch, construction expected to begin in Summer 2021
  • June 2021 - Project in design phase
  • July 2021 - 30% Complete, Limestone road is under construction leading up to the kayak launch. Road to be completed by Summer 2021
  • October 2021 - 100% Complete, Limestone road is completed leading up to the kayak launch.
  • November 2021 - Kayak Launch in late design phase.
  • May 2022 - Kayak Launch in late design phase and working on adjustments. We anticipate the following 5 month timeline for Manchac: 2 months – Complete construction documents and bidding; 3 months - Construction
  • February 2023 - The Bayou Manchac launch is nearly complete. This Blueway Launch and Trailhead allows paddlers to access Bayou Manchac via a floating dock system and wooden deck for fishing, birding and scenic views.
  • April 2023 - 100% Completed; project is completed, will be celebrating with ribbon cutting soon!

Completed Spring 2023


 

Previous Improvements

rendering of improvements to Bayou Manchac Park
Click image to enlarge

Features

  • NEW playground
  • NEW walking loop
  • NEW walking trail
  • NEW benches, picnic tables & water fountain
  • RENOVATED parking lots
  • IMPROVED nature trail

COMPLETED SUMMER 2019 (Click to view project timeline)

Project Updates:

  • April 2018 - Park identified for improvements
  • May 2018 - Online public input survey conducted
  • June 2018 - Schematic Design underway
  • July 2018 - Construction documents in progress
  • September 2018 - Out to bid
  • October 2018 - Bid awarded to The Luster Group LLC
  • January 2019 - Construction underway. Notice to Proceed issued to Luster Group January 7.
  • Febraury 2019 - 55% complete; concrete pours underway
  • March 2019 -  60% complete; concrete pours complete, playground equipment installed
  • April 2019 -  80% complete; Concrete walk complete, playground installed
  • June 2019 - 95% complete; Walk thru for substantial completion, last details to be completed - OPEN TO THE PUBLIC
  • July 2019 - 100% complete