N. 14th Street Park Improvements
New Features in Current Project Improvements:
- New/repaired windows & doors
- Possible Mural
- New Paint
- New Ornamental Fencing
- Reconfigured Basketball Court
Project Updates
- August 2018 - Design in development
- December 2018 - Permitting underway
- January 2019 - Scheduling lead abatement. Working on permit for major work.
- February 2019 - Construction underway by ANR Construction
- March 2019 - 7% - Building Painted, Fencing soon, some parallel parking finished
- April 2019 - 40%; Ornamental fencing up, waiting on doors and windows
- June 2019 - 80%; Doors and windows soon
- July 2019 - 90% - Doors and windows soon
- September 2019 - 95% - Windows installed
- November 2019 - 95% - Finalizing construction
- January 2020 - 98% - Finalizing construction
- February 2020 - Final signage, door removal, and interior painting Complete
COMPLETED SPRING 2020