North Sherwood Forest -- Project Page

Previous Improvements

Features

  • NEW playground shade sails

COMPLETED JANUARY 2021 (Click to view project timeline)

Project Updates:

  • SEPTEMBER 2019 - out to bid
  • NOVEMBER 2019 - Contracting
  • JANUARY 2020 - 5% Completed, under construction
  • FEBRUARY 2020 - 10% Completed, under construction
  • MAY 2020 - 15% Complete
  • JUNE 2020 - Most of the fencing has been erected.  Steel columns have arrived; project on hold until August
  • SEPTEMBER 2020 - 70% Complete, continuing construction of shade sails
  • NOVEMBER 2020 - 85% Complete, Continuing construction of shade sails
  • JANUARY 2021 - 100% Complete, Project completed 

 

North Sherwood Forest Community Park Rendered Master Plan

Features

  • NEW play area
  • NEW splash pad
  • NEW outdoor fitness equipment
  • NEW tennis court
  • NEW promenade/pond overlook
  • RENOVATED welcome/restroom building
  • NEW pavilions (4)
  • NEW signage
  • EXPANDED pond
  • ENHANCED fish habitat & fish cleaning station

COMPLETED MARCH 2018 (Click to view project timeline)

Project Updates:

  • 2004 - Public Meetings and Master Planning
  • 2005 - Family Recreation Center Renovations completed
  • NOVEMBER 2011 - Recreation Center Re-Roofing
  • 2012 - Site Infrastructure Construction completed - Asphalt drives & Parking Lots, Lighting
  • SPRING 2012 - Former BREC Administration Building Demolition
  • SUMMER 2013 2012 - Basketball Court, Pavilion, and Parking completed
  • 2014 - Tree Planting
  • JANUARY 2016 - Montoya Design Group hired to complete Master Plan through Construction Administration
  • MAY 26, 2016 - Bid approved by BREC commission
  • JULY 25, 2016 - Notice to Proceed issued J. Reed Constructor, Inc.
  • DECEMBER 2016 - Major dirt moving underway. Splash pad area is being formed up, flagpole and water feature bases are in.
  • MARCH 2017 - Splash pad, tennis court, flagpole, splash pad slab & feature bases, and pond complete. Site drainage, eletrical runs almost complete. Working on pavilions, fishing pier, forming & pouring walks
  • AUGUST 2017 - Significant rain delays experienced during this project. Several sections of concrete walks poured around the activity hub. Promenade pavers are in. Trellis is up and being painted.
  • SEPTEMBER 2017 - Play equipment installed, working on restroom building.
  • JANUARY 2018 - Grand Opening scheduled for March; final preparations underway
  • MARCH 2018 - Grand Opening held