River Bend Park - Improvements
New Features in Current Project Improvements:
- New playground
- Renovated walking loop
- Renovated pavilion
- New benches & water fountain
- Renovated tennis court
- New half basketball court
- Improved drainage
Project Updates
- June 2017 - Capital campaign concluded
- September 2017 - Construction documents in progress
- November 2017 - Bidding process underway
- January 2018 - Notice to Proceed issued to Acadian Constructors, Inc.
- April 2018 - Concrete nearly complete, playground drainage installed
- May 2018 - Playground installation & landscaping in progress
- June 2018 - Playground installation complete; wood fiber surfacing soon
- July 2018 - Construction mostly complete; grand opening prep underway
- September 2018 - Grand Opening held
COMPLETED JULY 2018