Milton J. Womack Park - Improvements
New Features in Current Project Improvements:
- New lighted multi-use fields
- New bleacher
- New restrooms
- New walks & paved parking lot
Project Updates
- May 2017 - Park identified for improvements; planning phase initiated.
- August 2017 - Design consultant starting on schematic design. Public input in September
- March 2017 - Bid opened
- May 2017 - Notice to Proceed issued to Industrial Enterprises Inc
- May 2018 - Substantially complete; working on grass grow
- June 2018 - equipment ordered; grand opening scheduled for August
- July 2018 - Permitting in progress
- August 2018 - Grand opening prep
- November 2018 - Grand Opening held
COMPLETED NOVEMBER 2018