Zachary Community Park - Improvements
July 2015
- Splash Pad documents – DHH permit received – Out to Bid, bid opens August 14
- Playground Area just starting – Ground-breaking held June 19
August 2015
- Splash Pad Bid opened August 14 within budget
- Playground Area – 30% complete
September 2015
- Splash Pad Bid Notice to Proceed Oct 1
- Playground Area – 25% complete
October 2015
- Splash Pad Bid Notice to Proceed Oct 19
- Playground Area – 30% complete
November 2015
- Playground Area – 50% complete
- Splash Pad Bid – Construction starting
December 2015
- Playground Area – 60% complete
- Splash Pad Bid – 40% complete
January 2016
- Playground Area – 80% complete
- Splash Pad Bid – 75% complete
February 2016
- Playground Area – 90% complete
- Splash Pad Bid – 90% complete
April 2016
- Grand Opening for playground/splash pad held April 22